Task
Glazing the superstructure in a very short time
Solution
Our regular customer approached us with the task of glazing the superstructure in a very short time – 1.5 months. The task was complicated by the work in the winter. The aluminum frame was assembled in 2 weeks. During this time, the double-glazed windows were manufactured in batches, which were installed 2 weeks after the completion of the frame.
All the work was carried out in 6 weeks. A total of 190 sq. m. of glazing.
Everything was completed within the specified time.
The customer is satisfied. We are satisfied too.